|
Getting your Trinity Audio player ready...
|

Across the Waikato district, roading crews have been out early, working late, and making the most of every dry window, council says.
The Waikato District Council general manager of assets and infrastructure, Megan May, says that despite a challenging run of weather, its summer resealing and maintenance programme is tracking ahead of schedule.
“When you feel that smoother surface under your tyres, that’s months of planning and hard mahi coming together.
“Our contractors — Higgins in the north and Fulton Hogan in the south — have worked at pace right across the district. They’ve adapted quickly to changing weather and kept the momentum going. That’s something worth celebrating.”
So far this summer, the council has delivered 66.5km of road resealed of the 96.35km planned across the district, with work already completed in areas like Maramarua, Te Kauwhata, and Pukekawa.
Every kilometre resealed protects your road from water damage. It prevents potholes. It extends the life of the surface. And it saves money in the long run by avoiding bigger rebuilds later, May says.
But this summer hasn’t been straightforward.
Periods of wet and unsettled weather meant contractors have had to change plans quickly. Resealing can’t happen in the rain. The surface must be dry so the new layer bonds properly.
“When conditions changed, crews shifted locations and adjusted schedules to make the most of fine days. That flexibility is one reason we’re still ahead of schedule.
“We know road works can slow you down. Temporary traffic management, loose chip and detours aren’t ideal. But by getting ahead now, we reduce the risk of more disruptive repairs later. We’re protecting your investment and building resilience into our network.”
Over the coming weeks, crews will continue work in Pokeno, Port Waikato, Glen Murray, Onewhero, and Otaua.



